Concrete Mix Cost & Slump Estimator
Know what your
mix actually costs.
Enter your plant's real quantities and delivered prices. This tool returns cost per cubic yard and cubic meter, an absolute-volume yield check, an ACI 211-based screening slump estimate, the ACI 305 surface evaporation rate and a combined aggregate gradation check — in any mix of US and metric units.
Not sure where to start, or what each section does?
- Any unit system
- Absolute-volume yield
- ACI 211 slump screening
- ACI 305 evaporation rate
- Tarantula gradation check
- Pre-quote review checks
Placing conditions
Will the surface dry faster than it bleeds?
The ACI 305 surface evaporation rate: how fast water leaves the top of the pour. Above 1.0 kg/m²/h — the same threshold as the familiar 0.2 lb/ft²/h — plastic shrinkage cracking becomes likely and precautions are required.
Sensitivity at this surface temperature — humidity down, wind across
The equation covers temperature, humidity and wind only. It does not include solar radiation, shading, surface texture or any fogging already in place, so on a clear day treat the figure as a floor rather than a ceiling — and judge the real risk on the surface itself: loss of sheen, early crusting, plastic cracking.
Mix settings
Set the basis for the batch
Design targets
What the mix is meant to hit
Enter the specified targets and the report shows them beside what your proportions actually produce, flagging anything outside tolerance. Design strength is recorded and printed — it is not predicted from the mix.
Materials & plant prices
Your mix design, your delivered prices
Quantities and prices can each use whichever unit your plant works in — the tool converts everything internally. Admixtures dosed in fl oz/cwt or mL/100 kg rebase automatically on total cementitious content. Uncheck a row to exclude it without losing the values.
| Include | Material | Category | Quantity | Qty unit | Unit cost | Cost unit | Sp. gravity | $ / yd³ | Remove |
|---|
Cost summary
What a yard costs you
Cost contribution
Where the money goes
Each active material's share of as-entered material cost, largest first.
Mix design checks
Does the mix close on volume?
Absolute volumes are computed from mass and specific gravity, plus entrained air. A theoretical yield of 27 ft³ means the batch makes exactly one cubic yard.
Slump estimator
ACI 211-based screening estimate
The estimator reads your batch water against ACI 211's approximate mixing-water demand for the selected aggregate size and air condition, then applies your plant corrections. It is a planning aid, not an acceptance result.
Gradation
Is the combined aggregate workable?
The Tarantula Curve, from Cook and Ley at Oklahoma State. Enter percent passing from each aggregate’s sieve report; the blend comes from the batch weights above. Passing is not a guarantee of workability — the developers pair it with the Box Test — but failing it reliably predicts a mix that is hard to place or finish.
Percent retained on each sieve. The two dark lines are the published upper and lower limits — the envelope the curve is named after — and the orange line is this mix. A filled marker is a sieve outside the envelope.
Checks
Review before this price goes out
These look for the failure modes that produce a plausible-looking but wrong number — a price charged against a quantity the row does not carry, a material taking up no space, a yield nowhere near 27 ft³, a slump estimate that has hit the display limit, gradation data that cannot be physically correct.
Materials library
Your materials, your suppliers
Set a material up once with its source, SSD specific gravity and price, then drop it into any mix instead of retyping. Shared with your colleagues; VeroTouch products are included and priced by us.
Saved mixes
Pick up where you left off
Saved to your company account and shared with your colleagues. VeroTouch cannot see them.
Quality control
Turn your test readings into a report
Enter what you measured on the pour and what the cylinders broke at. The report presents your own readings — it is not a certified test result.
| Age, days | Cyl 1 | Cyl 2 | Cyl 3 | Average psi | % of design |
|---|
Report letterhead
Your logo on every report
Reports you generate carry your branding, not ours. PNG or JPG, up to 2 MB.
Your report
Take the numbers with you
Download this mix as a spreadsheet-ready CSV and a full PDF report — every input, every conversion, the cost and slump breakdown, and your quality-control readings.
Report unlocked.
Method & limits
ACI 318 is a structural design code and contains no slump-prediction equation. This estimator uses ACI 211 proportioning water-demand relationships as its reference, then applies the plant corrections you enter. Predicted slump is a screening figure for planning only — it is never an acceptance result. Verify fresh concrete with the current ASTM C143/C143M procedure. Project specifications, approved mixture submittals, and your quality-control program govern production and acceptance. Costs reflect only the quantities and prices you enter here.